20 switches carefully replaced between Luxembourg and Pétange

engineering works/projects
// 9 April 2025

Friday 4 April 2025 saw the end of a major phase of maintenance work on the Luxembourg – Bascharage-Sanem – Rodange- Athus respectively Longwy lines. Following the replacement of 10,000 concrete sleepers in November 2024, 20 new switches were installed between 14 March and 4 April 2025.

As a reminder, the CFL had decided, as a precaution, to replace the concrete sleepers that had a manufacturing defect causing a chemical phenomenon known as ‘alkali-silica’.

The operations at the end of 2024 were carried out at a rate of 200 concrete sleepers replaced on average every hour. On the other hand, the switches need to be replaced individually because of the precise interlocking of the rails and the turnout drives, which means that the work has to be carried out partly by hand, and therefore required a second phase of work in spring 2025.

Read more:
Switches: simply explained
The tamping machine: Millimeter work on the track
The ballast plough: A ballast redistribution working machine