The Hollerich mobility hub (PM Hollerich) is an integral part of the projects set out in the National Mobility Plan (PNM 2035). Following Pfaffenthal-Kirchberg and Howald, Hollerich will become the third mobility hub to be developed in the suburban belt surrounding Luxembourg City. This additional mobility hub will help reduce car traffic in the capital by encouraging the use of public transport. It will also strengthen the role of the Hollerich district within the capital’s mobility strategy.
With a projected capacity of 16,000 passengers by 2035, this new infrastructure is designed to anticipate the demographic and economic development of the capital. The Hollerich mobility hub also aim at anticipating the future “Nei Hollerich” and “Porte de Hollerich” districts into Luxembourg City’s urban development projects.

The redevelopment of the western part of Luxembourg Central Station and the construction of the Hollerich mobility hub will improve the punctuality and reliability of train services between the capital and the west of the country. Once the works have been completed, each of the railway lines serving the Hollerich mobility hub will have two separate dedicated tracks between Hollerich and Luxembourg.
As part of the planned works, an additional track will be constructed between Hollerich and Luxembourg Central Station for the Luxembourg – Bascharage-Sanem – Rodange – Athus/Longwy line. This will reduce the need for trains on this line to cross paths with trains from other lines at the country’s busiest railway station, helping to improve the fluidity and punctuality of rail traffic.
Following the reorganisation of the track plan, passengers travelling on the Luxembourg – Kleinbettingen – Arlon line will also benefit from regular stops at Hollerich, as passengers on the Luxembourg – Bascharage-Sanem – Rodange – Athus/Longwy line did in the past.
The mobility hub will make connections between trains and other forms of public transport easier, including Luxembourg City buses, the tram and regional RGTR buses. The many passengers travelling to Cessange, Hollerich, Ban de Gasperich, Cloche d’Or or the future “Nei Hollerich” and “Porte de Hollerich” districts will be able to reach their destination without systematically continuing their journey to Luxembourg Central Station.
Thanks to the Hollerich mobility hub, train passengers will be able to easily access nearby bus services via barrier-free connections, in particular at Route d’Esch, Rue de la Déportation, Rue de Cessange and Rue Maurice-Barrès.

The new mobility hub will also facilitate access to the planned extension projects of the tram.
The new mobility hub also takes into account the needs of passengers wishing to combine cycling and public transport. A secure indoor bikebox facility providing 350 bicycle spaces will be available in the access building on Route d’Esch.

Passengers using the Hollerich mobility hub will benefit from completely rebuilt platforms whose width will facilitate the movement of several thousand people. The new platforms will be at least 250 metres long and covered by canopies to provide protection from the weather, while offering sufficient space to accommodate high-capacity trains with more seating.
All access points to the different areas of the Hollerich mobility hub will be barrier-free and equipped with the necessary facilities to provide comprehensive passenger information and ensure a smooth and comfortable journey.
In the new passenger building to the west of Route d’Esch, passengers will also benefit from commercial facilities, modern waiting areas and sanitary facilities





The existing railway stop will be replaced by a new station as part of the new mobility hub in Hollerich. The new station will be built to the west of the existing railway stop and will be supported by a load-bearing structure consisting of railway bridges, allowing landscaped areas to be created beneath the bridges.
The works will include, among others:
As part of the works on the Hollerich mobility hub, the existing railway stop will be taken out of service to allow the necessary works to be carried out on its southern and northern sides, including work on the track platform and the complete reconfiguration of the track plan.
These works will be carried out alternately on the Luxembourg – Kleinbettingen – Arlon and Luxembourg – Bascharage-Sanem – Rodange – Athus/Longwy lines between 2027 and 2032. Construction of the platforms and access buildings, as well as the external landscaping works, will take place between 2032 and 2034.
Passengers who would normally continue their journey from Hollerich are asked to travel as far as Luxembourg Central Station and use the Luxembourg City (AVL) bus network from there.
To allow the works to progress efficiently and ensure that they can be carried out safely, changes to train services and temporary closures of the Luxembourg – Kleinbettingen – Arlon and Luxembourg – Bascharage-Sanem – Rodange – Athus/Longwy lines will be necessary throughout the project.
Although most of these works will be carried out during school holidays, when passenger numbers are lower and the buses required to provide replacement services are available, interruptions to rail traffic and adjustments to train services will nevertheless be necessary.
Details of the closure periods planned for 2027 are available in the interactive works calendar on the CFL website and in the CFL go app. Details of rail replacement bus services will be published on the CFL website before the works begin.
The total cost of constructing the new mobility hub is estimated at €280 million, of which €20 million will be financed by the City of Luxembourg.